FERC said in a filing dated February 27 that it has approved Venture Global Plaquemines LNG’s requests to commission and introduce hazardous fluids to liquefaction block 9 and pretreatment Unit C.
In August 2024, FERC granted the commissioning of the liquefaction train system block 1, while the regulator approved the commissioning of the liquefaction train system block 8 earlier this month.
Venture Global recently also received approval from FERC to boost the capacity of its Plaquemines LNG terminal in Louisiana to 27.2 mtpa.
The company took a final investment decision on the first phase of the Plaquemines project with a capacity of 13.3 mtpa and the related pipeline in May 2022.
In March 2023, the company sanctioned the second phase of the Plaquemines LNG export plant in Louisiana and also secured $7.8 billion in project financing.
The full project, including the second stage, will have a capacity of 20 mtpa coming from 36 modular units, configured in 18 blocks.
Each train has a capacity of 0.626 mtpa.
Venture Global said in its IPO statement it is targeting a COD (commercial operations date) for the Plaquemines project in the third quarter of 2026 for Phase 1 and the second quarter of 2027 for Phase 2.
The company started producing LNG at the Plaqumines LNG plant on December 13, 2025, and the first shipment left the facility to Germany some two weeks after that.
Venture Global delivered at least three Plaquemines LNG commissioning cargoes up to date to Germany.
Shipping data shows that the LNG plant has been shipping about two cargoes per week in February.
The post Venture Global to introduce gas to 9th Plaquemines liquefaction block appeared first on Energy News Beat.
“}]]