April 28

Cheniere’s Corpus Christi expansion project 82.5 percent complete

0  comments

[[{“value”:”

Cheniere’s Corpus Christi plant currently liquefies natural gas at three operational trains, each with a capacity of about 5 mtpa.

In June 2022, Cheniere made the final investment decision on the Corpus Christi Stage 3 expansion project, worth about $8 billion, while compatriot Bechtel officially started construction on the project in October of the same year.

The project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

In March 2025, Cheniere achieved substantial completion of the first liquefaction train at the Corpus Christi Stage 3 expansion project.

Cheniere’s unit, Corpus Christi Liquefaction, said in the March construction report filed with the US FERC on Friday that the overall project completion rate for Stage 3 is 82.5 percent.

The project was 80 percent complete at the end of February this year.

Stage 3 engineering and procurement were 98.2 percent and 99.8 percent complete as of the end of March 2025, respectively, while subcontract and direct hire construction work were 89.8 percent and 53.7 percent complete, respectively.

During March, key work fronts included aboveground piping in Train 2 – 6 and outside boundary limits (OSBL), concrete pours in Trains 2 – 7, structural steel erection in Trains 2 – 7 and OSBL, underground piping installation in Trains 5 – 7 and OSBL, and equipment setting in Trains 2 – 7.

CCL said additional continued work includes road improvements, drainage work, and mobilization of temporary facilities, equipment, and personnel.

During April, Bechtel will continue concrete foundations and pedestal works and other works in Trains 2-5, while it will continue excavation to support the upcoming concrete pours in Trains 6-7.

Train 2 cryogenic rack (Image: Cheniere)

Upon substantial completion of all seven trains of CCL Stage 3 in 2026, the expected total production capacity of the Corpus Christi liquefaction facility will be over 25 mtpa of LNG.

In addition to this expansion, Cheniere recently received approval from FERC to build two more midscale trains at its Corpus Christi LNG plant.

Cheniere is also seeking approval from FERC to start site preparation activities for the trains.

The proposed midscale trains 8 and 9 project or project includes adding two midscale
liquefaction trains, each with an expected liquefaction capacity of about 1.49 mtpa, and associated facilities, as well as increasing the authorized loading rate at the terminal’s existing marine berth.

In February, Cheniere CEO Jack Fusco confirmed that the company still expects to make a final investment decision to build two more midscale trains at its Corpus Christi LNG plant this year.

The post Cheniere’s Corpus Christi expansion project 82.5 percent complete appeared first on Energy News Beat.

“}]] 

​Energy News Beat 


Tags


You may also like

How Gold Imports Blew up Atlanta Fed GDPNow: The Old Model is Dead, Long Live the “New GDPNow Model” Starting Apr 30

How Gold Imports Blew up Atlanta Fed GDPNow: The Old Model is Dead, Long Live the “New GDPNow Model” Starting Apr 30